Constantine decides not to refurbish fire station

Constantine Village Council members last week decided against refurbishing the municipality’s fire station.

Village manager Mark Honeysett submitted an estimate of $39,000 from Roberts Brothers Excavating to demolish the building and remove all concrete. A conservative estimate shows it would cost nearly $267,000 to rehabilitate the station.

Honeysett recommended relocating the fire department to the site of the former D&S, at 175 Washington Street. The village purchased the building in 2018 after foreclosure for non-payment of taxes.

Check Also

Sheriff’s department looking for information on unresponsive man found in Lockport Township

St. Joseph County Sheriff’s Department is hoping security footage might provide a clue into the …

Leave a Reply

Your email address will not be published. Required fields are marked *